Section 4A
- windows up to the 11th floor are installed;
- completed plastering work on all floors;
- completed work on the arrangement of interior partitions;
- work on the wiring of electrical cables and the installation of electrical panels is nearing completion;
- arrangement of a chimney on the roof.
Section 4B
- the overlap of the second floor is completed;
- preparation for the erection of the walls of the third floor.
Section 4B
- foundation work is underway.
Section 4G
- plumbing works completed;
- installed radiators up to the 6th floor;
- a laser floor screed up to the 5th floor was made;
- underfloor heating system laid up to the 6th floor;
- the insulation of the facade from the side of the courtyard has been completed;
The adjoining territory
- completed the arrangement of the playground;
- gates are installed from the side of section 4G and 4D;
- the playground is covered with a traumatic rubber coating.