Based on the results of our team's work, 2024 can be safely called the year of housewarming.
The construction of the Idilika Avenue residential complex was completed and put into operation, most of the construction of which falls on the time of full-scale invasion.
Three sections of the Millennium State residential complex (4D, 4A and 4G) were put into operation and the issuance of ownership documents to investors began.
In 2023, we began construction of the new Millennium Park residential complex. According to the results of 2024, 9 floors of the first section of the complex and 5 floors of the second section have already been built. And this means that
investors of this complex have also become closer to getting their own home. In 2025, our team continues to work on the development of residential complexes, creating quality housing for Ukrainians and improving the life of the Buchanan community.
Idilika Avenue Residential Complex
The main event of 2024 for us was the completion of construction and commissioning of the Idilika Avenue residential complex. Today, many families are already preparing for housewarming, and the first establishments have already started operating on the first floor.
You can estimate the amount of work performed in 2024 using this abbreviated list:
- A transformer substation was installed and assembled;
- A gas control point was installed and assembled;
- A pump unit was installed and assembled;
- Elevator cabins were installed and sheathed;
- Chimney pipes were installed in apartments;
- Dual-circuit gas boilers were installed in all apartments;
- Gas network was laid;
- The front group was decorated;
- Stretch ceilings were installed in common areas throughout sections;
- Decorative elements and video surveillance cameras were installed;
- Facade work on commercial premises was completed;
- Work on laying tiles on the floor of the shopping center was completed;
- An intercom system was installed on the entrances;
- Lights and emergency backup lighting were installed in common areas;
- LED lighting was installed on the roof parapets;
- Barriers were installed;
- Street lighting was installed on the adjacent territory;
- A decorative fence was installed on the closed adjacent territory and landscaping was done;
- Paving tiles were laid on the adjacent territory and parking lots places.
Millennium State Residential Complex
Section 4D, 4A and 4G
- The section has been put into operation and the process of issuing ownership documents has begun.
Section 4B
- We have completed the installation of windows;
- The elevator equipment has been fully installed, elevator doors have been installed and two elevators are being tested;
- The plastering work has been completed in the entire section (by apartment and in common areas);
- We have completed the filling of the apartments in accordance with the contracts from the developer, and we are also continuing work on additional filling from investors (plumbing, heating and electricity);
- We have begun installing water and electricity panels in public areas;
- Preparatory work is underway for laying tiles in the entrance group of the entrance (elevator exit).
Section 4B
- The laying of all 11 floors has been successfully completed, the building has a completely finished appearance;
- Electrical wiring has been made throughout the section;
- We are starting work on pouring the screed on the roof and waterproofing;
- A system of storm drains has been laid in the section;
- The screed has been poured on all public balconies;
- A waterproofing membrane has been installed on the roof;
- The installation of windows from the inner facade of the section has been completed;
- The installation of doors on the cold balconies has been completed transition.
Millennium Park Residential Complex
Across the complex
- We are completing the work on laying external communication systems (water supply, gas supply, sewage).
Section 1
- Masonry from the 1st to the 9th floor has been completed;
- Masonry of interior partitions has been completed;
- Electrical wiring in common areas from the 2nd to the 7th floor inclusive.
Section 2
- We have completed pouring concrete entrance groups on the basement floor;
- Monolithic stairs to the bomb shelters and storage rooms have been poured;
- Masonry from the 1st to the 5th floors has been completed;
- The 5th floor has been covered with slabs and brickwork has begun on the 6th floor.