Section 3D
- completed installation of elevators
- painted corridor walls
- are being installed mailboxes
- work in progress Cleaning
Section 4A
- works on installation of windows
- installed protective railings cold
- junction,construction of interior walls
- being constructed parapets
Section 4B
- completion of waterproofing the basement
- complete fill Laying nets basement
- preparatory works before the construction of the wall
section 4D
- completed installation of windows on all floors of
- interior walls built
- continues internal plastering of walls from 6th to 11th floors
- construction of parapets is completed
Section 4D
- completion of painting of interfloor stairs and railings of all floors
- cleaning work is carried out in the entrance
- elevators are installed The
adjoining territory is
- equipped and a fountain is connected
- around the residential complex; parking spaces are marked;is nearing
- the planting of trees around the housecompletion