Section 3D
- Elevators are being installed.
- Work continues on laying ceramic tiles in public areas.
- Work is underway on priming the entrance groups before applying decorative plaster.
- The finishing works on the arch are nearing completion.
- The finishing works of the entrances are in progress.
Section 4D
- Facade works from the side of the courtyard are being completed.
- Completed painting of the corridors.
- The laying of ceramic tiles in common areas has been completed.
- The floors are being cleaned.
- Work continues on the installation of elevators.
- Work is underway to finish the entrances.
Section 4A
- The filling of the reinforcement layer of the 9th floor has been completed.
- Bricklaying of the 10th floor is underway.
- Installation of windows on the 1st floor is in progress.
Section 4G
- The filling of the reinforcement layer of the 10th floor has been completed.
- Brickwork on the 11th floor is underway.
- The installation of windows on the 4th floor is in progress.
Section 4B
- Foundation works are in progress.
Territory improvements
- Works on the arrangement of the courtyard is underway.
- Preparatory work for the laying of paving slabs is underway near the 3D section.
- Paving slabs have been laid near section 4D.
- Work is underway to install ceramic tiles in commercial premises.