Section 3D
- Works on installation of elevators сontinue
- Work on laying ceramic tiles in common areas сontinue
- Works on priming the entrance groups before applying decorative plaster are being completed
- Works on the arch is being completed
- Workw on the entrances is being completed
Section 4D
- Facade work on the side of the courtyard is being completed
- Painting corridors is being completed
- Laying ceramic tiles in common areas is being completed
- Floors are being cleaned
- Ongoing lift installation works
Section 4A
- Completed fill laying nets floor 9
- Brickwork in floor 10 is being completed
- Held installation of windows 1 floor
section 4D
- Casting floor laying nets 10 is being completed
- Being brickwork floor 11 сontinue
- Continues the installation of windows 4 floor
section 4B
- Continue foundation works
Territory improvements
- Works arrangement of the courtyard
- Preparatory work for laying paving slabs underway Near 3D section
- Near section 4D completed paving slabs laying
- Work on laying the tile near the commercial areas