Report on the progress of the construction of the Millennium State LCD and the work performed in September 2019
In section a
- completed masonry floors
- roofing works are ending
- facade decoration started
- installation of windows is nearing completion
- breeding plumbing continues
- internal plastering work in progress
- preparation of the territory for improvement
In Section B
- work is underway to connect to the gas network.
In Section B
- work is underway to connect to the gas network.
In Section D
- facade decoration completed
- interior plastering is being completed
- sand screed device is completed
- preparation of the territory for landscaping has begun
- work on the installation of entrance doors
In Section D
- preparation for installation of crane equipment
In Section 4D
- there is a bricklaying 2 floors
- completed installation of crane equipment