New photo report on the state of construction of the Millennium State.
In section A
- there is a brickwork of 11 floors
In Section B
- work on connection to the gas network is underway
In Section B
- the process of installing boilers is in progress
keys are being issued
In Section G
- installation of facing tiles in corridors
- facade works are carried out
- installation of windows on 8-11 floor
- stucco works are being carried out on the 7th floor
In Section D
- completed the brickwork of partitions in the basement
In Section 4D
- the brickwork of the 1st floor continues
On the street Nazarii Yaremchuk work is being done on the road arrangement and landscaping.