Section 3D
- lightning protection system is installed
- elevators connected
- mailboxes are installed
- work on cleaning entrance groups is completed
Section 4A
- installed window to 6 floors
- is working on plaster above 6 floor
- installed interior partitions to 7 floors
- work is underway for wiring electric cables and arrangement switchboard
Section 4B
- works on the overlap of the first floor
- preparation for the erection of walls of the second floor
Section 4G
- being actively plumbing
- radiators up to the 4th floor
- door installed a cold junction
- system of floor heating installed in 3 floor
Section 4D
- running elevators
- complete cleaning of entrances
Territory improvements
- set frame playgrounds and sports grounds
- held landscaping
- cover agropolotnomplants
- installed left exit gates and preparation for the installation of the right gate of the entrance to the territory of the complex