Section 3D
- facade work being completed by the court
- continues plumbing work
- from first to sixth floors are completed work on pouring the floor screed
- installation of gas hoods begins
- installation of doors
- installation of protective panels on cold passages
Section 4D
- completed installation of doors
- completed pouring of the floor screed
- up to the 6th floor, the laying of ceramic tiles in common areas is completed
Section 4A
- the brickwork of the seventh floor continues
Section 4G
- the brickwork of the eighth floor continues