Section 3D
- Active work is underway on installation and glazing of windows on the 2nd, 3rd and 8th floors.
- Work continues on the internal plastering of the walls of the 7th floor.
Section 4D
- Facade works are in progress.
- Installation of windows is in progress.
- Plumbing work is underway.
- Underfloor heating is being installed.
Section 4A
- Bricklaying of the 1st floor is underway.
Section 4G
- The work of the basement overlap continues.
- Completed work on the installation of vertical waterproofing.