Section 3D:
- Active construction of parapets is underway.
- Work continues on the installation of windows.
Section 4D
- Roofing works are completed.
- Completed installation of windows from the courtyard side.
- The work on the internal plastering of the walls of the 9th floor is being completed.
- Completed laying of internet cables.
Section 4A
- Vertical waterproofing was installed.
Section 4G:
- Foundation work in progress.
We installed and painted the gates, thereby closing the territory of the complex.