Section 3D
- Active brickwork of the 11th floor is underway.
- The internal plastering of the entrance to the 5th floor has been completed.
- Internet and electrical cables are being laid.
Section 4D
- Installation of membrane roofing is completed.
- Internal plastering works on the 5th and 11th floors are in progress.
- Electric cables are being laid.
Section 4A
- Active work is underway on the installation of foundation blocks.
Section 4G
- Work is underway to build a foundation pit.