In section A
- elevator installation was completed
- installation tile was completed in common areas
- tile laying continues on stairwells
- preparation of corridors for painting
- works on installation of gas pipes is completed
In Section G
- installation of elevators continues
- installation of gas pipes continues
In Section D
- brickwork on 7th floor
- brickwork of internal interroom partitions on 2-3 floors
In Section 4D
- brickwork on 8th floor
- installation of windows on 2-3 floors
- brickwork of internal interroom partitions on 5-6 floors
- completed the filling of the armored belt on the 7th floor undergoing
In Section 4A
- preparatory work on the basement