The construction of the Millennium State, 16.04.19

New Millennium State Photo Report.
As of April 15, 2007:

In Section A
1. There is a brickwork on the 7th floor and installation of windows on the 5th floor.

In Section B

1. Lifts are mounted and started. The cabin of the cargo elevator is covered with protective material.
2. The final cleaning and decoration of public places is carried out.

In Section B

1. Lifts are mounted and started. The cabin of the cargo elevator is covered with protective material.
2. Finishing the facade with decorative plaster.
3. Finished finishing of the entrance group, namely laying ceramic tiles on stairs and ramps.
4. The final cleaning and decoration of public places is carried out.

The installation of the adjoining territory of Sections B and Sections B continues: the arrangement of curbs and laying of sidewalk tiles is underway.

In Section G.

1. There is a brick laying on the 11th floor.
2.Massage of interiors and interiors partitions is performed in parallel.
3. A finishing plaster of 6 floors is underway.
4.The installation of windows 6th floor is started.

In Section D.

There is a brick masonry of 3 floors and internal partitions.

In Section 4D
The foundation has been completed.

We invite you to visit your city under the sun: (095) 509 00 75; (063) 661 61 90!
More information on the official website: mlstate.com.ua